Page updated February 11, 2010
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Roof | June 1, 2011 | August 31, 2011 |
| Seal Building Exterior | June 1, 2010 | August 31, 2010 |
| Replace Windows | June 1, 2010 | September 30, 2010 |
| Replace Flooring | June 1, 2010 | August 31, 2010 |
| Upgrade Fire Alarm | June 1, 2010 | August 31, 2010 |
| Replace Gym Floor | June 1, 2011 | August 31, 2011 |
| Resurface Playground | July 20, 2009 | August 10, 2009 |
| Resurface Parking Lot | June 1, 2010 | August 31, 2010 |
Replace Roof |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Top of page
Seal Building Exterior |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public School
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Windows |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public School
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date September 30, 2010 |
Top of page
Replace Flooring |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public School
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Fire Alarm |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public School
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Upgrade Gym Floor |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
Estimated Finish Date August 31, 2011 |
Top of page
Resurface Playground |
Scope |
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 20, 2009 |
Estimated Finish Date August 10, 2009 |
Top of page
Resurface Parking Lot |
Scope |
Project Managers |
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Wright Elementary
4060 Lone Oak Road SE
Salem, OR 97302
Map