Page updated May 11, 2010
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Roof | June 21, 2010 | August 31, 2010 |
| Seal Building Exterior | June 21, 2010 | August 31, 2010 |
| Replace Windows | June 21, 2010 | August 31, 2010 |
| Replace Floor Coverings | June 21, 2010 | August 31, 2010 |
| Replace Portions of Siding | June 21, 2010 | September 30, 2010 |
| Replace Damaged Ceiling Tiles | June 21, 2010 | August 31, 2010 |
| Partition Walls in Eight Classrooms | June 21, 2010 | August 31, 2010 |
| Replace Water Supply Lines | June 21, 2010 | August 31, 2010 |
| Resurface Portions of Parking Lot | July 16, 2009 | August 4, 2009 |
| Repair/Replace Heating and Ventilation Units | June 21, 2010 | August 31, 2010 |
Replace Roof |
Scope |
Project Managers - Brian Radabaugh, Cornerstone Management Group
|
Architect - Paul L. Bentley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Seal Building Exterior |
Scope - Complete exterior painting and seal
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Windows |
Scope - 100% replacement of existing windows
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Floor Coverings |
Scope - Abate asbestos
- 100% replacement of existing flooring
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Portions of Siding |
Scope - Repair approximately 30% of existing siding
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date September 30, 2010 |
Top of page
Replace Damaged the Ceiling Tiles |
Scope - Repair and replace ceiling tiles
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Partition Walls in Eight Classrooms |
Scope - Replacement of accordion curtain walls in eight classrooms with new sheetrock walls
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Water Supply Lines |
Scope - Replacement of hot water lines throughout the school
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Resurface Portions of Parking Lot |
Scope |
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Start Date July 16, 2009 |
Finish Date August 4, 2009 |
Top of page
Repair/Replace Heating and Venilation Units |
Scope - Repair and balancing of HVAC system
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 21, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page