Page updated December 7, 2009
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Sealed Building Exterior | August 8, 2009 | August 31, 2009 |
| Replace Windows | June 2, 2010 | September 30, 2010 |
| Replace Damaged Siding | July 20, 2009 | August 24, 2009 |
| Replace Damaged Ceiling Tiles | June 2, 2010 | August 31, 2010 |
| Replace the Gym Floor | June 2, 2010 | July 31, 2010 |
| Replace Water Supply Lines | June 2, 2010 | August 31, 2010 |
| Resurface Playground | June 1, 2010 | August 31, 2010 |
Seal Building Exterior |
Scope - Replace compromised siding (see siding job below)
- Clean entire exterior of school, portables, gym, and covered play shed building(s)
- Clean exteriors of portables and covered play shed
- Seal and protect exterior brick
- Paint exterior of main building, portables and portions of gym and covered play shed
|
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date August 8, 2009 |
| Estimated Finish Date August 31, 2009 |
Top of page
Replace Half the Windows |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 2, 2010 |
| Estimated Finish Date September 30, 2010 |
Top of page
Replace Damaged Siding |
Scope - Replace compromised siding
- Add new siding to match existing siding
- Enhance siding to roof transitions as needed
|
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date July 20, 2009 |
| Estimated Finish Date August 24, 2009 |
Top of page
Replace Half the Ceiling Tiles |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 2, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Replace the Gym Floor |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 2, 2010 |
| Estimated Finish Date July 31, 2010 |
Top of page
Replace Water Supply Lines |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 2, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Resurface Playground |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Washington Elementary
3165 Lansing Avenue NE
Salem, OR 97301-8639
Map