Waldo Middle School

Page updated May 11, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Seal Building Exterior June 22, 2009July 17, 2009
Replace WindowsJune 21, 2010September 30, 2010
Replace Majority of Floor CoveringsJune 21, 2010August 31, 2010
Replace Water Supply Lines June 21, 2010August 31, 2010
Resurface Parking Lot  June 21, 2010August 31, 2010

 

 

Seal Building Exterior
 

Scope 

  • Clean entire exterior of school and gym building(s)
  • Paint entire exterior of school, gym and portable

Project Managers

  • John Abel, Cornerstone Management Group
  • Stephanie Farthing,  Construction Services, Salem-Keizer Public Schools

Architect

  • Carlson-Veit Architects

Contractor

  • All Star Paint
Estimated Start Date June 22, 2009
Estimated Finish Date July 17, 2009

Top of page

 

  

 

Replace Windows
 

Scope

Project Managers

  •  Mathieu Jacobs, Cornerstone Management Group
  •  Art Merriman, Construction Services, Salem-Keizer Public Schools

Architect

  •  Paul L. Bentley Architects

Contractor

  •  LCG Pence
  •  
Estimated Start Date June 21, 2010
Estimated Finish Date September 30, 2010

Top of page

 

 

 

Replace Majority of Floor Coverings
 

Scope

Project Managers

  •  Mathieu Jacobs, Cornerstone Management Group
  •  Art Merriman, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Paul L. Bentley Architects

Contractor

  •  LCG Pence
  •  
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010

Top of page

 

 

 

Replace Water Supply Lines
 

Scope

Project Managers

  •  Mathieu Jacobs, Cornerstone Management Group
  •  Art Merriman, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Paul L. Bentley Architects

Contractor

  •  LCG Pence
  •  
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010

Top of page

 

 

 

Resurface Parking Lot
 

Scope

Project Managers

  •  Mathieu Jacobs, Cornerstone Management Group
  •  Art Merriman, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Paul L. Bentley Architects

Contractor

  •  LCG Pence
  •  
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010

Top of page

 

Waldo MIddle
2805 Lansing Avenue NE
Salem, OR 97301-8555
Map

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions