| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Portions of Roof | June 22, 2009 | July 31, 2009 |
| Replace Exterior Seal | June 4, 2012 | August 31, 2012 |
| Replace Half the Windows | June 4, 2012 | August 31, 2012 |
| Replace the Siding | June 4, 2012 | August 31, 2012 |
| Replace Majority of Floor Coverings | June 4, 2012 | August 31, 2012 |
| Replace Portion of Celing Tiles | June 4, 2012 | August 31, 2012 |
| Replace Gym Floor | June 4, 2010 | August 31, 2010 |
| Repair Damaged Asphalt on Playground | July 6, 2009 | August 21, 2009 |
Replace Exterior Seal |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Half the Windows |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace the Siding |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Majority of Floor Coverings |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Portions of Ceiling Tiles |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |