Summer 2009 bond project list released

Submitted by Michelle Harryman on June 19, 2009 - 6:44pm

Tags: bond update, elementary, high school, middle school

Last updated 2009-09-28

Summer Bond List

Summer repair projects at 48 schools are mostly completed. The repairs are funded by the school construction bond approved by voters in November 2008. 

 School

Job Description Start Contractor Finished Date
Auburn WindowsTBAArciform8/21/09
Auburn Window abatement8/1/09  8/21/09
Chapman Hill Parking lot6/28/09Guerney (Cemex)8/24/09
Chapman Hill Roof7/8/09Arrow Roofing8/25/09
Clear LakeSoffits replacement6/25/09DGS General8/14/09
CrosslerExterior paint6/22/09Williamson & Blied8/18/09
CummingsFlooring6/20/09Thomas Kay8/10/09
CummingsFloor abatement 7/14/09Rose City 8/14/09
EnglewoodExterior paint7/13/09Fitzpatrick8/10/09
EnglewoodPlayground surface6/29/09H&H Paving8/10/09
Four CornersRoof6/25/09McDonald Wettle7/24/09
Four CornersPlayground resurface6/29/09North Santiam8/10/09
HayesvilleParking lot7/1/09JM Long8/4/09
Hazel GreenRoof6/22/09ABC Roofing8/12/09
HighlandTuck point on masonry7/16/09Pioneer Waterpro 9/16/09
HighlandParking lot7/13/09Cascade Paving8/10/09
HooverWindowsSummer 2010Team Construction Postponed
HooverParking lot & playground7/6/09H&H Paving8/10/09
HooverWindow abatement7/15/09IRS Environmental 7/15/09
KennedyParking lot7/2/09JM Long8/4/09
Lake LabishPlayground7/6/09Cascade Paving8/4/09
LibertyPipe replacement7/9/09CJ Hanson8/24/09
LibertyPipe abatement7/1/09IRS Environmental 7/7/09
McKayStadium bleachers11/30/09 2KG 
McKinleyExterior paint6/22/09All Star Paint6/29/09
McNaryRoof6/15/09Umpqua Roofing8/19/09
McNaryStadium bleachers11/30/09 2KG 
McNaryParking lot7/2/09Houck Construction8/19/09
Middle GroveExterior paint4/11/09All Star Paint4/20/09
Middle Grove Siding for paint7/1/09DGS General7/2/09
Middle Grove Water line replacement6/26/09Collins Mechanical8/14/09 
North Salem HSTuck point on masonry7/16/09Pioneer Waterpro 
North Salem HSStadium bleachers11/30/09 2KG 
PringleRoof7/6/09Arrow Roofing8/14/09
PringleParking lot7/13/09Cascade Paving 9/10/09
RichmondTuck point on masonry 7/21/09  9/1/09
RosedalePlayground7/20/09Cascade Paving 8/10/09
Salem HeightsRoof6/16/09McGilchrist & Sons8/17/09
SchirleExterior doors6/30/09Rich Duncan 9/13/09
SchirleExt. door abatement7/20/09  7/24/09
South Salem HSStadium lights6/30/09Portland Electric8/13/09
SpragueExterior paint6/16/09Williamson & Blied8/21/09
SpragueStadium bleachers7/7/09Greenberry 8/28/09
SumpterFire alarm7/6/09SecureCom8/7/09
SwegleRoof6/22/09ABC Roofing7/31/09 
SweglePlayground7/6/09Cascade Paving 9/1/09
WaldoExterior paint6/22/09All Star Paint7/17/09
WashingtonExterior paint8/10/09Fitzpatrick 8/28/09
WashingtonSiding7/20/09   8/21/09
WhiteakerParking lot7/06/09Cascade Paving8/4/09
WrightPlayground7/20/09H&H Paving8/10/09
YoshikaiSoffits replacement6/25/09American Vault8/18/09
Yoshikai Flooring6/29/09Thomas Kay8/15/09

 

  • Download the Summer 2009 Bond Projects List (164 KB PDF)

Visit the Construction Bond Updates Web site for more information on bond projects.

  • Share this

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions