Summer 2009 bond project list released
Last updated 2009-09-28
Summer repair projects at 48 schools are mostly completed. The repairs are funded by the school construction bond approved by voters in November 2008.
School | Job Description | Start | Contractor | Finished Date |
| Auburn | Windows | TBA | Arciform | 8/21/09 |
| Auburn | Window abatement | 8/1/09 | 8/21/09 | |
| Chapman Hill | Parking lot | 6/28/09 | Guerney (Cemex) | 8/24/09 |
| Chapman Hill | Roof | 7/8/09 | Arrow Roofing | 8/25/09 |
| Clear Lake | Soffits replacement | 6/25/09 | DGS General | 8/14/09 |
| Crossler | Exterior paint | 6/22/09 | Williamson & Blied | 8/18/09 |
| Cummings | Flooring | 6/20/09 | Thomas Kay | 8/10/09 |
| Cummings | Floor abatement | 7/14/09 | Rose City | 8/14/09 |
| Englewood | Exterior paint | 7/13/09 | Fitzpatrick | 8/10/09 |
| Englewood | Playground surface | 6/29/09 | H&H Paving | 8/10/09 |
| Four Corners | Roof | 6/25/09 | McDonald Wettle | 7/24/09 |
| Four Corners | Playground resurface | 6/29/09 | North Santiam | 8/10/09 |
| Hayesville | Parking lot | 7/1/09 | JM Long | 8/4/09 |
| Hazel Green | Roof | 6/22/09 | ABC Roofing | 8/12/09 |
| Highland | Tuck point on masonry | 7/16/09 | Pioneer Waterpro | 9/16/09 |
| Highland | Parking lot | 7/13/09 | Cascade Paving | 8/10/09 |
| Hoover | Windows | Summer 2010 | Team Construction | Postponed |
| Hoover | Parking lot & playground | 7/6/09 | H&H Paving | 8/10/09 |
| Hoover | Window abatement | 7/15/09 | IRS Environmental | 7/15/09 |
| Kennedy | Parking lot | 7/2/09 | JM Long | 8/4/09 |
| Lake Labish | Playground | 7/6/09 | Cascade Paving | 8/4/09 |
| Liberty | Pipe replacement | 7/9/09 | CJ Hanson | 8/24/09 |
| Liberty | Pipe abatement | 7/1/09 | IRS Environmental | 7/7/09 |
| McKay | Stadium bleachers | 11/30/09 | 2KG | |
| McKinley | Exterior paint | 6/22/09 | All Star Paint | 6/29/09 |
| McNary | Roof | 6/15/09 | Umpqua Roofing | 8/19/09 |
| McNary | Stadium bleachers | 11/30/09 | 2KG | |
| McNary | Parking lot | 7/2/09 | Houck Construction | 8/19/09 |
| Middle Grove | Exterior paint | 4/11/09 | All Star Paint | 4/20/09 |
| Middle Grove | Siding for paint | 7/1/09 | DGS General | 7/2/09 |
| Middle Grove | Water line replacement | 6/26/09 | Collins Mechanical | 8/14/09 |
| North Salem HS | Tuck point on masonry | 7/16/09 | Pioneer Waterpro | |
| North Salem HS | Stadium bleachers | 11/30/09 | 2KG | |
| Pringle | Roof | 7/6/09 | Arrow Roofing | 8/14/09 |
| Pringle | Parking lot | 7/13/09 | Cascade Paving | 9/10/09 |
| Richmond | Tuck point on masonry | 7/21/09 | 9/1/09 | |
| Rosedale | Playground | 7/20/09 | Cascade Paving | 8/10/09 |
| Salem Heights | Roof | 6/16/09 | McGilchrist & Sons | 8/17/09 |
| Schirle | Exterior doors | 6/30/09 | Rich Duncan | 9/13/09 |
| Schirle | Ext. door abatement | 7/20/09 | 7/24/09 | |
| South Salem HS | Stadium lights | 6/30/09 | Portland Electric | 8/13/09 |
| Sprague | Exterior paint | 6/16/09 | Williamson & Blied | 8/21/09 |
| Sprague | Stadium bleachers | 7/7/09 | Greenberry | 8/28/09 |
| Sumpter | Fire alarm | 7/6/09 | SecureCom | 8/7/09 |
| Swegle | Roof | 6/22/09 | ABC Roofing | 7/31/09 |
| Swegle | Playground | 7/6/09 | Cascade Paving | 9/1/09 |
| Waldo | Exterior paint | 6/22/09 | All Star Paint | 7/17/09 |
| Washington | Exterior paint | 8/10/09 | Fitzpatrick | 8/28/09 |
| Washington | Siding | 7/20/09 | 8/21/09 | |
| Whiteaker | Parking lot | 7/06/09 | Cascade Paving | 8/4/09 |
| Wright | Playground | 7/20/09 | H&H Paving | 8/10/09 |
| Yoshikai | Soffits replacement | 6/25/09 | American Vault | 8/18/09 |
| Yoshikai | Flooring | 6/29/09 | Thomas Kay | 8/15/09 |
- Download the Summer 2009 Bond Projects List (164 KB PDF)
Visit the Construction Bond Updates Web site for more information on bond projects.