Complete List of School Repairs
| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Heating and Ventilation Ducts | June 1, 2011 | December 31, 2011 |
| Replace Exterior Seal | June 16, 2009 | August 21, 2009 |
| Replace Half the Floor Coverings | June 1, 2011 | August 31, 2011 |
| Replace Damaged Wooden Bleacher Seats/Concrete Steps | July 7, 2009 | August 28, 2009 |
| Repair/Resurface Damaged Parking Lot | June 1, 2011 | August 31, 2011 |
| Repair and Replace Auditorium Lighting Panels | June 1, 2011 | August 31, 2011 |
Replace Heating and Ventilation Ducts |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date December 31, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Half the Floor Coverings |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Repair/Resurface Damaged Parking Lot |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Repair and Replace Auditorium Lighting Panels |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |