South Salem High School

Page updated May 11, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace Portions of Roof July 1, 2010August 31, 2010
Replace Heating/Ventilation System June 21, 2010November 30, 2010 
Replace Exterior Seal Completed 2008Completed 2008
Replace Majority of Windows June 21, 2010September 30, 2010
Replace Damaged Floor Coverings  June 21, 2010September 30, 2010 
Replace Damaged Ceiling Tiles  June 21, 2010September 30, 2010
Repair and Refurbish Locker Rooms  June 21, 2010August 31, 2010
Replace Half the Water Supply Lines June 21, 2010   September 30, 2010
Replace Electrical Panels in Gym and Annex  June 21, 2010  October 31, 2010
Resurface Parking Lot June 21, 2010August 31, 2010
Repair/Replace Theater Lighting Control Panels June 21, 2010October 31, 2010
Replace Stadium Lights  June 30, 2009August 13, 2009

 

  

Replace Portions of Roof
 

Scope

Project Managers

  •  Brian Radabaugh, Cornerstone Management Group

Architect

  •  Paul L. Bentley Architects

Contractor

  •  ABC Roofing
Estimated Start Date July 1, 2010
Estimated Finish Date August 31, 2010

Top of page

 

 

  

Replace Heating/Ventilation System
 

Scope

  • Abate asbestos
  • Refurbish fans, motors and belts
  • Replace failing pneumatic controls with a DDC system

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • Oregon Cascade
Estimated Start Date June 21, 2010
Estimated Finish Date November 30, 2010
 

Top of page

 

 

  

Seal Building Exterior
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date Completed 2008
Estimated Finish Date Completed 2008

Top of page

 

 

  

Replace Majority of Windows
 

Scope

  • Remove existing glass block and replace with thermally improved window systems
  • Remove existing steel sash windows and replace with thermally improved window systems 

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • Capitol City Glass
  • Southtown Glass
Estimated Start Date June 21, 2010
Estimated Finish Date September 30, 2010
 

Top of page

 

 

  

Replace Damaged Floor Coverings

Scope

  • Abate asbestos
  • Remove asbestos flooring and replace with vinyl composition tile

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • Thomas Kay
Estimated Start Date June 21, 2010
Estimated Finish Date September 30, 2010
 

Top of page

 

 

  

Replace Ceiling Tiles

Scope

  • Patch and paint selected ceilings
  • Replace selected drop-in ceilings

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • PCI/Shields
Estimated Start Date June 21, 2010
Estimated Finish Date September 30, 2010
 

Top of page

 

 

  

Repair and Refurbish Locker Rooms
 

Scope

  • Remove floor finish and replace with new
  • General repairs to HVAC, plumbing and tile finishes
  • Paint walls and ceilings

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010
 

Top of page

 

  

 

Replace Half the Water Supply Lines
 

Scope

  • Abate asbestos
  • Replace galvanized plumbing lines with copper to improve water quality

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • Willamette Plumbing
Estimated Start Date June 21, 2010
Estimated Finish Date September 30, 2010
 

Top of page

 

  

 

Replace Electric Panels in Gym and Annex

Scope

  • Replace selected electrical panels

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • Portland Electric
Estimated Start Date June 21, 2010
Estimated Finish Date October 31, 2010
 

Top of page

 

  

 

Resurface Parking Lot 
 

Scope

  • Resurface and repair existing parking lots and bus loop

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • North Santial Paving
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010
 

Top of page

 

 

  

Repair/Replace Theater Lighting Control Panels
 

Scope

Project Managers

  •  Cheryl Pin, Cornerstone Management Group
  •  Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  •  Arbuckle Costic Architects

Contractor

  •  LCG Pence
  • Portland Electric
Estimated Start Date June 21, 2010
Estimated Finish Date October 31, 2010

Top of page

 

 

  

Replace Stadium Lights
 

Scope

  • Completely remove existing lights, poles, and electrical services at Bennett Field. Replace with new low-spill lighting and pull power off of existing building service.

Project Managers

  • Cheryl Pin, Cornerstone Management Group
  • Richard Clausen, Construction Services, Salem-Keizer Public Schools 

Architect

  • Arbuckle Costic Architects

Contractor

  • Portland Electrical
Estimated Start Date June 30, 2009
Estimated Finish Date August 13, 2009

Top of page

 

South Salem High School
1910 Church Street SE
Salem, OR 97302
Map

 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions