Page updated November 24, 2009
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Portions of Roof | July 1, 2010 | August 31, 2010 |
| Replace Heating/Ventilation System | June 1, 2010 | November 30, 2010 |
| Replace Exterior Seal | Completed 2008 | Completed 2008 |
| Replace Majority of Windows | June 1, 2010 | September 30, 2010 |
| Replace Damaged Floor Coverings | June 1, 2010 | September 30, 2010 |
| Replace Damaged Ceiling Tiles | June 1, 2010 | September 30, 2010 |
| Repair and Refurbish Locker Rooms | June 1, 2010 | August 31, 2010 |
| Replace Half the Water Supply Lines | June 1, 2010 | September 30, 2010 |
| Replace Electrical Panels in Gym and Annex | June 1, 2010 | October 31, 2010 |
| Resurface Parking Lot | June 1, 2010 | August 31, 2010 |
| Repair/Replace Theater Lighting Control Panels | June 1, 2010 | October 31, 2010 |
| Replace Stadium Lights | June 30, 2009 | August 13, 2009 |
Replace Portions of Roof |
Scope |
Project Managers - Brian Radabaugh, Cornerstone Management Group
|
Architect - Paul L. Bentley Architects
|
Contractor |
| Estimated Start Date July 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Replace Heating/Ventilation System |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date November 30, 2010 |
Top of page
Seal Building Exterior |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date Completed 2008 |
| Estimated Finish Date Completed 2008 |
Top of page
Replace Majority of Windows |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date September 30, 2010 |
Top of page
Replace Damaged Floor Coverings |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date September 30, 2010 |
Top of page
Replace Ceiling Tiles |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date September 30, 2010 |
Top of page
Repair and Refurbish Locker Rooms |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Half the Water Supply Lines |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date September 30, 2010 |
Top of page
Replace Electric Panels in Gym and Annex |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date October 31, 2010 |
Top of page
Resurface Parking Lot |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Repair/Replace Theater Lighting Control Panels |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date October 31, 2010 |
Top of page
Replace Stadium Lights |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 30, 2009 |
| Estimated Finish Date August 13, 2009 |