Schirle Elementary School
Page updated November 24, 2009
Complete List of School Repairs
| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Roof | June 1, 2010 | August 31, 2010 |
| Replace Heating/Ventilation Rooftop Units/Chiller | June 1, 2011 | August 31, 2011 |
| Replace Doors and Door Frames | June 30, 2009 | September 13, 2009 |
| Replace Floor Coverings | June 1, 2011 | August 31, 2011 |
| Replace Hot Water Lines | June 1, 2011 | August 31, 2011 |
| Upgrade Fire Alarms | June 1, 2011 | August 31, 2011 |
| Upgrade Master Clock | June 1, 2011 | August 31, 2011 |
Replace Roof |
Scope |
Project Managers
|
Architect
|
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Replace Heating/Ventilation Rooftop Units/Chiller |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Floor Coverings |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Hot Water Lines |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Fire Alarm |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Upgrade Master Clock |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |