Richmond Elementary School

Page updated May 18, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace Roof 

June 21, 2010

August 31, 2010
Replace Exterior Seal June 1, 2011August 31, 2011 
Replace Half the Windows June 1, 2011August 31, 2011
Replace Brick Mortar July 21, 2009September 1, 2009
Replace Floor Coverings June 1, 2011August 31, 2011 
Replace Ceiling Tiles June 1, 2011August 31, 2011
Replace Water Supply Lines  June 1, 2011 September 30, 2011 
Replace Bathroom Fixtures  June 1, 2011 September 30, 2011 
Replace Damaged Asphalt on Playground  June 1, 2011 August 31, 2011 

 

  

Replace Roof
 

Scope

Project Managers

  •  Brian Radabaugh, Cornerstone Management Group  

Architect

  •  Paul L. Bentley Architects

Contractor

  •  Griffith Roofing
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010

Top of page

 

  

 

Replace Exterior Seal
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011

Top of page

 

  

 

Replace Half the Windows
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011

Top of page

 

  

 

Replace Brick Mortar
 

Scope   

  • Remove and replace failing tuck-point of brick exterior
  • Reseal repaired areas

Project Managers

  • John Abel, Cornerstone Management Group
  • Stephanie Farthing,  Construction Services, Salem-Keizer Public Schools

Architect

  • Carlson-Veit

Contractor

  •  
Estimated Start Date July 21, 2009
Estimated Finish Date September 1, 2009

Top of page

 

  

 

Replace Floor Coverings
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011

Top of page

 

  

 

Replace Ceiling Tiles
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011

Top of page

 

  

Replace Water Supply Lines
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011

Top of page

 

 

  

Replace Bathroom Fixtures
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011

Top of page

 

  

 

Replace Damaged Asphalt on Playground
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011

Top of page

 

Richmond Elementary
466 Richmond Avenue SE
Salem, OR 97301
Map 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions