Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Portions of Roof | June 1, 2011 | August 31, 2011 |
| Replace a Portion Windows | May 3, 2010 | October 31, 2010 |
| Replace Floor Coverings | June 21, 2010 | August 31, 2010 |
| Replace Damaged Ceiling Tiles | June 21, 2010 | August 31, 2010 |
| Seal Building Exterior | June 21, 2010 | August 31, 2010 |
| Repair and Seal Brick Mortar on Building Exterior | July 21, 2009 | September 30, 2009 |
| Replace Wiring | May 3, 2010 | November 1, 2010 |
| Upgrade Fire Alarm System | TBD | TBD |
| Replace Emergency Generator | May 3, 2010 | November 1, 2010 |
| Replace Stadium Bleachers | November 30, 2009 | April 2010 |
| Resurface Damaged Parking Lot | June 21, 2010 | August 31, 2010 |
| Replace Water Pipes | May 3, 2010 | November 1, 2010 |
| Replace Theater Lighting Control Panels | May 3, 2010 | November 1, 2010 |
Replace Portions of Roof |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Top of page
Replace a Portion of Windows |
Scope - Replace original single pane windows with thermally improved window systems
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Beeline
|
| Estimated Start Date May 3, 2010 |
Estimated Finish Date October 31, 2010 |
Top of page
Replace a Portion of Floor Coverings |
Scope - Abate asbestos
- Remove battleship linoleum in halls and classes that is original to the building and replace with vinyl composition tile
- Remove asbestos flooring and replace with vinyl composition tile
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Thomas Kay
|
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Damaged Ceiling Tiles |
Scope - Patch and paint selected ceilings
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Harlens
|
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Seal Building Exterior |
Scope - Provide new paint and brick sealer around the exterior of the biulding
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Benchmark
|
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Repair and Seal Brick Mortar on Building Exterior |
Scope - Repair mortar (tuck-pointing) on 50% of school and reseal repaired areas
|
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date July 21, 2009 |
Estimated Finish Date September 30, 2009 |
Top of page
Replace Wiring |
Scope - Replace original electrical panels
- Replace branch wiring that is original to the building
- Replace hallway lighting
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Cherry City Electric
|
| Estimated Start Date May 3, 2010 |
| Estimated Finish Date November 1, 2010 |
Top of page
Replace Fire Alarm System |
Scope - Replace existing fire alarm system
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Cherry City Electric
|
| Estimated Start Date TBD |
Estimated Finish Date TBD |
Top of page
Replace Emergency Generator |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Cherry City Electric
|
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |
Top of page
Replace Stadium Bleachers |
Scope - Replace wooden bleachers with aluminum units
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date November 30, 2009 |
Estimated Finish Date April 2010 |
Top of page
Resurface Damaged Parking Lot |
Scope - Repair and resurface existing parking lots
|
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- KF Jacobson
|
| Estimated Start Date June 21, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Water Pipes |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Judson's
|
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |
Top of page
Replace Theater Lighting Control Panels |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arcbuckle Costic Architects
|
Contractor - Howard S. Wright Construction Co.
- Cherry City Electric
|
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |