Page updated November 24, 2009
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Portions of Roof | June 1, 2011 | August 31, 2011 |
| Replace a Portion Windows | May 3, 2010 | October 31, 2010 |
| Replace Floor Coverings | June 1, 2010 | August 31, 2010 |
| Replace Damaged Ceiling Tiles | June 1, 2010 | August 31, 2010 |
| Seal Building Exterior | June 1, 2010 | August 31, 2010 |
| Repair and Seal Brick Mortar on Building Exterior | July 16, 2009 | September 30, 2009 |
| Replace Wiring | May 3, 2010 | November 1, 2010 |
| Upgrade Fire Alarm System | May 3, 2010 | November 1, 2010 |
| Replace Emergency Generator | May 3, 2010 | November 1, 2010 |
| Replace Stadium Bleachers | November 30, 2009 | April 2010 |
| Resurface Damaged Parking Lot | June 1, 2010 | August 31, 2010 |
| Replace Water Pipes | May 3, 2010 | November 1, 2010 |
| Replace Theater Lighting Control Panels | May 3, 2010 | November 1, 2010 |
Replace Portions of Roof |
Scope |
Project Managers - Brian Radabaugh, Cornerstone Management Group
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace a Portion of Windows |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date May 3, 2010 |
Estimated Finish Date October 31, 2010 |
Top of page
Replace a Portion of Floor Coverings |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Damaged Ceiling Tiles |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Seal Building Exterior |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Repair and Seal Brick Mortar on Building Exterior |
Scope - Repair mortar (tuck-pointing) on 50% of school and reseal repaired areas
|
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date July 16, 2009 |
Estimated Finish Date September 30, 2009 |
Top of page
Replace Wiring |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date May 3, 2010 |
| Estimated Finish Date November 1, 2010 |
Top of page
Replace Fire Alarm System |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |
Top of page
Replace Emergency Generator |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect - Arbuckle Costic Architects
|
Contractor |
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |
Top of page
Replace Stadium Bleachers |
Scope - Replace wooden bleachers with aluminum units
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date November 30, 2009 |
Estimated Finish Date April 2010 |
Top of page
Resurface Damaged Parking Lot |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Water Pipes |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |
Top of page
Replace Theater Lighting Control Panels |
Scope |
Project Managers - Cheryl Pin, Cornerstone Management Group
- Richard Clausen, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date May 3, 2010 |
Estimated Finish Date November 1, 2010 |
Top of page
North Salem High
765 14th Street NE
Salem, OR 97301-2611
Map