Myers Elementary School

Page updated May 11, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace RoofJune 1, 2011August 31, 2011
Replace Heating/Ventilation Roof-top Unit/ChillerJune 21, 2010August 31, 2010
Replace Damaged Floor CoveringsJune 21, 2010August 31, 2010
Replace Gym Floor June 1, 2011 August 31, 2011
Replace Damaged Asphalt on Playground June 21, 2010 August 31, 2010

 

  

Replace Roof
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

  

 

Replace Heating/Ventilation Roof-top Unit/Chiller
 

Scope

  • Replace chiller and and cooling tower
  • Replace pneumatic HVAC controls with DDC controls
  • Repair and upgrade existing air handling units

Project Managers

  •  John Abel, Cornerstone Management Group
  •  Stephanie Farthing, Construction Services, Salem-Keizer Public Schools  

Architect

  •  Carlson-Veit Architects

Contractor

  •  Brockamp & Jaeger, Inc.
  • CJ Hansen Co., Inc.
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010 

Top of page

 

  

 

Replace Damaged Floor Covering
 

Scope

  • Replace 90% of floor coverings

Project Managers

  •  John Abel, Cornerstone Management Group
  •  Stephanie Farthing, Construction Services, Salem-Keizer Public Schools  

Architect

  •  Carlson-Veit Architects

Contractor

  •  Brockamp & Jaeger, Inc.
  • Fabulous Floors
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010
 

Top of page

 

 

  

Replace Gym Floor
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

  

 

Replace Damaged Asphalt on Playground
 

Scope

  • Improve drainage on outside play areas
  • Resurface and restripe asphalt play areas

Project Managers

  •  John Abel, Cornerstone Management Group
  •  Stephanie Farthing, Construction Services, Salem-Keizer Public Schools  

Architect

  •  Carlson-Veit Architects

Contractor

  •  Brockamp & Jaeger, Inc.
  • H & H Paving Co.
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010 

Top of page

 

Myers Elementary
2160 Jewel Street NW
Salem, OR 97304
Map 

 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions