Page updated October 14, 2009
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Roof | June 1, 2011 | August 31, 2011 |
| Replace Heating/Ventilation Roof-top Unit/Chiller | June 1, 2010 | August 31, 2010 |
| Replace Damaged Floor Coverings | June 1, 2010 | August 31, 2010 |
| Replace Gym Floor | June 1, 2011 | August 31, 2011 |
| Replace Damaged Asphalt on Playground | June 1, 2010 | August 31, 2010 |
Replace Roof |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
Estimated Finish Date August 31, 2011 |
Top of page
Replace Heating/Ventilation Roof-top Unit/Chiller |
Scope |
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Replace Damaged Floor Covering |
Scope |
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Gym Floor |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
Estimated Finish Date August 31, 2011 |
Top of page
Replace Damaged Asphalt on Playground |
Scope |
Project Managers - John Abel, Cornerstone Management Group
- Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Myers Elementary
2160 Jewel Street NW
Salem, OR 97304
Map