McKinley Elementary School

Page updated May 11, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace Exterior Seal June 22, 2009 June 29, 2009
Replace Floor Coverings June 1, 2011August 31, 2011
Replace Old Gym Floor June 21, 2010August 31, 2010
Replace Sewer Lines June 1, 2011September 30, 2011
Replace Water Supply Lines  June 1, 2011September 30, 2011
Replace Bathroom Fixtures  June 1, 2011September 30, 2011
Replace Master Clock  June 1, 2011August 31, 2011

 

Replace Exterior Seal
 

Scope

  • Completely paint and seal the exterior of the school and gymnasium

Project Managers

  • John Abel, Cornerstone Management Group
  • Stephanie Farthing,  Construction Services, Salem-Keizer Public Schools

Architect

  • ACA Architects

Contractor

  • All Star Paint
Estimated Start Date July 1, 2009
Estimated Finish Date Summer 2009
 

Top of page

 

  

Replace Floor Coverings
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

  

Replace Old Gym Floor
 

Scope

  • Demo existing floor
  • Repair and prep sub-floor
  • Install new two-part polyurethane floor and striping

Project Managers

  •  John Abel, Cornerstone Management Group
  •  Stephanie Farthing, Constuction Services, Salem-Keizer Public Schools  

Architect

  •  Carlson-Veit Architects

Contractor

  •  Team Construction
  • T&T
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010
 

Top of page

  

Replace Sewer Lines
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011

Top of page

  

Replace Water Supply Lines

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011
 

Top of page

  

Replace Bathroom Fixtures
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011

Top of page

  

Replace Master Clock
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

McKinley Elementary
466 McGilchrist Street SE
Salem, OR 97302
Map

 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions