Home

Salem-Keizer Public Schools

Oregon School District 24J

Dropdowns

  • Emergency Closures/Delays
  • Jobs
  • Strategic Plan
  • Volunteer
Home > Departments > Facilities & Planning > Bond Construction Updates > Schools
    • Calendar
    • Contact
    • Help

Construction Bond Photos

McKinley - BEFORE replacing exterior seal - June 2009
McKinley - AFTER replacing exterior seal - June 2009

McKinley Elementary School

Page updated November 24, 2009

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace Exterior Seal June 22, 2009 June 29, 2009
Replace Floor Coverings June 1, 2011August 31, 2011
Replace Old Gym Floor June 1, 2010August 31, 2010
Replace Sewer Lines June 1, 2011September 30, 2011
Replace Water Supply Lines  June 1, 2011September 30, 2011
Replace Bathroom Fixtures  June 1, 2011September 30, 2011
Replace Master Clock  June 1, 2011August 31, 2011

 

Replace Exterior Seal
 

Scope

  • Completely paint and seal the exterior of the school and gymnasium

Project Managers

  • John Abel, Cornerstone Management Group
  • Stephanie Farthing,  Construction Services, Salem-Keizer Public Schools

Architect

  • ACA Architects

Contractor

  • All Star Paint
Estimated Start Date July 1, 2009
Estimated Finish Date Summer 2009
 

Top of page

 

  

Replace Floor Coverings
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

  

Replace Old Gym Floor
 

Scope

Project Managers

  •  John Abel, Cornerstone Management Group
  •  Stephanie Farthing, Constuction Services, Salem-Keizer Public Schools  

Architect

  •  Carlson-Veit Architects

Contractor

  •  
Estimated Start Date June 1, 2010
Estimated Finish Date August 31, 2010
 

Top of page

  

Replace Sewer Lines
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011

Top of page

  

Replace Water Supply Lines

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011
 

Top of page

  

Replace Bathroom Fixtures
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date September 30, 2011

Top of page

  

Replace Master Clock
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

McKinley Elementary
466 McGilchrist Street SE
Salem, OR 97302
Map

 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Photo Gallery
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us

Salem-Keizer Public Schools 2450 Lancaster Dr. NE, Salem, Oregon, 97305   503-399-3000.