Page updated November 24, 2009
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Portions of Roof | June 1, 2011 | August 31, 2011 |
| Repair/Replace Heating/Ventilation System | June 1, 2010 | August 31, 2010 |
| Seal Building Exterior | June 1, 2010 | August 31, 2010 |
| Replace Portions of Windows | June 1, 2010 | August 31, 2010 |
| Replace Floor Coverings | June 1, 2010 | August 31, 2010 |
| Replace Water Supply Lines | July 9, 2009 | August 24, 2009 |
| Upgrade Fire Alarms | June 1, 2010 | August 31, 2010 |
| Resurface Parking Lot | June 1, 2010 | August 31, 2010 |
Replace Portions of Roof |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Top of page
Repair/Replace Heating/Ventilation System |
Scope |
Project Managers - Christy Stockton, Cornertsone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Seal Building Exterior |
Scope |
Project Managers - Christy Stockton, Cornertsone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Portions of Windows |
Scope |
Project Managers - Christy Stockton, Cornertsone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Floor Coverings |
Scope |
Project Managers - Christy Stockton, Cornertsone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Water Supply Lines |
Scope - Replacing all the cold water lines in the building
|
Project Managers - Brian Radabaugh, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor - CJ Hanson and abatement by IRS Environmental
|
| Estimated Start Date July 9, 2009 |
Estimated Finish Date August 24, 2009 |
Top of page
Upgrade Fire Alarms |
Scope |
Project Managers - Christy Stockton, Cornertsone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Resurface Parking Lot |
Scope |
Project Managers - Christy Stockton, Cornertsone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Liberty Elementary
4871 Liberty Road S
Salem, OR 97306-2418
Map