Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Part of Roof | June 1, 2010 | August 31, 2010 |
| Replace Exterior Seal | June 4, 2012 | August 31, 2012 |
| Replace Windows | Summer 2010 | Summer 2010 |
| Replace Floor Coverings | June 4, 2012 | August 31, 2012 |
| Replace Gym Floor | June 4, 2010 | August 31, 2010 |
| Replace Hot Water Lines | June 4, 2012 | September 28, 2012 |
| Replace Fire Alarms | June 4, 2012 | August 31, 2012 |
| Repair Playground | July 6, 2009 | August 8, 2009 |
| Resurface Part of Parking Lot | July 6, 2009 | August 8, 2009 |
| Replace Damaged Ceiling Tiles | June 4, 2012 | August 31, 2012 |
Replace Part of Roof |
Scope |
Project Managers - Brian Radabaugh, Cornerstone Management Group
|
Architect - Paul L. Bentley Architects
|
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Exterior Seal |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Top of page
Replace Windows |
Scope - Replacing old single pane windows with energy efficient units
- Seismic upgrades to structure
|
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect - Anderson Shirley Architects
|
Contractor |
| Estimated Start Date Summer 2010 |
| Estimated Finish Date Summer 2010 |
Top of page
Replace Majority of Floor Coverings |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
Estimated Finish Date August 31, 2012 |
Top of page
Replace Gym Floor |
Scope |
Project Managers - Christy Stockton, Cornerstone Management Group
- Mike Witte, Constuction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 4, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace Hot Water Lines |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date September 28, 2012 |
Top of page
Upgrade Fire Alarm |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Top of page
Replace Damaged Asphalt on Playground |
Scope - Resurfacing playground
- Repainting of activity areas
|
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date July 6, 2009 |
Estimated Finish Date August 8, 2009 |
Top of page
Resurface Portions of Parking Lot |
Scope - Resurface a portion of the north parking lot
- Correct drainage issues
|
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date July 6, 2009 |
| Estimated Finish Date August 8, 2009 |
Top of page
Replace Damaged Ceiling Tiles |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
Estimated Finish Date August 31, 2012 |