Highland Elementary School

Page updated May 18, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace RoofJune 21, 2010August 31, 2010
Replace Exterior SealJune 4, 2012August 31, 2012
Replace Half the Brick MortarJuly 16, 2009September 16, 2009
Replace Ceiling TilesJune 4, 2012August 31, 2012
Replace Gym Floor June 4, 2012August 31, 2012
Replace Bathroom Fixtures June 1, 2012September 30, 2012
Replace Electrical Wiring June 4, 2012 August 31, 2012
Repair Parking Lot July 6, 2009 August 10, 2009

 

 

Replace Roof

Scope

Project Managers

  •  Brian Radabaugh, Cornerstone Management Group  

Architect

  •  Paul L. Bentley Architects

Contractor

  •  McDonald & Wetle
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010

Top of page

 

 

 

Replace Exterior Seal
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 4, 2012
Estimated Finish Date August 31, 2012
 

Top of page

 

 

 

Replace Half the Brick Mortar

Scope 

  • Repair mortar (tuck-pointing) and reseal repaired areas

Project Managers

  • Mathieu Jacobs, Cornerstone Management Group
  • Mike Witte,  Construction Services, Salem-Keizer Public Schools

Architect

  • Anderson Shirley

Contractor

  • Pioneer Waterpro
Estimated Start Date July 16, 2009
Estimated Finish Date September 16, 2009
 

Top of page

 

 

 

Replace Ceiling Tiles

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 4, 2012
Estimated Finish Date August 31, 2012
 

 Top of page

 

 

 

Replace Gym Floor

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 4, 2012
Estimated Finish Date August 31, 2012

 

 Top of page

 

  

 

Replace Bathroom Fixtures

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 4, 2012
Estimated Finish Date September 30, 2012
 

 Top of page

 

  

 

Replace Electrical Wiring

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 4, 2012
Estimated Finish Date August 31, 2012
 

 Top of page

 

 

 

Repair Parking Lot

Scope 

  • Resurfacing a portion of the north parking lot

Project Managers

  • Mathieu Jacobs, Cornerstone Management Group
  • Mike Witte,  Construction Services, Salem-Keizer Public Schools

Architect

  • Anderson Shirley

Contractor

  • Cascade Paving
Estimated Start Date July 6, 2009 
Estimated Finish Date August 10, 2009

Top of page

 

Highland Elementary
530 Highland Avenue NE
Salem, OR 97303
Map

 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions