| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Roof | June 1, 2011 | August 31, 2011 |
| Replace Exterior Seal | June 1, 2012 | August 30, 2012 |
| Replace Half the Siding | June 1, 2012 | August 30, 2012 |
| Replace Gym Floor | June 1, 2012 | August 30, 2012 |
| Resurface Damaged Parking Lot | July 1, 2009 | August 31, 2009 |
Replace Roof |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Exterior Seal |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2012 |
| Estimated Finish Date August 30, 2012 |
Replace Half the Siding |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Gym Floor |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2012 |
| Estimated Finish Date August 31, 2012 |