Fruitland Elementary School
Last updated September 16, 2009
Complete List of School Repairs
| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Heating/Ventilation Ducts | June 4, 2012 | August 31, 2012 |
| Replace Exterior Seal | June 4, 2012 | August 31, 2012 |
| Replace Majority of Windows | June 4, 2012 | August 31, 2012 |
| Replace Majority of Siding | June 4, 2012 | August 31, 2012 |
| Resurface Water Supply Line from Well | June 4, 2012 | August 31, 2012 |
Replace Heating/Ventilation Ducts |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Exterior Seal |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Majority of Windows |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Replace Majority of Siding |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |
Resurface Water Supply Line from Well |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 4, 2012 |
| Estimated Finish Date August 31, 2012 |