Last updated November 19, 2009
Complete List of School Repairs
Projects
| Estimated Start Date
| Estimated Completion Date
|
| Replace Portions of Roof | June 25, 2009 | July 24, 2009 |
| Seal Building Exterior | June 1, 2010 | October 31, 2010 |
| Replace a Portion Windows | June 1, 2010 | August 31, 2010 |
| Replace a Portion Siding | June 1, 2010 | August 31, 2010 |
| Replace a Portion of Floor Coverings | June 1, 2010 | August 31, 2010 |
| Replace a Portion of Ceiling Tiles | June 1, 2010 | August 31, 2010 |
| Replace a Portion of Bathroom Fixtures | April 30, 2010 | October 31, 2010 |
| Replace a Portion of Water Supply Lines | April 30, 2010 | October 31, 2010 |
| Upgrade Fire Alarm System | June 1, 2010 | August 31, 2010 |
| Resurface Playground | June 29, 2009 | August 10, 2009 |
Replace Portions of Roof |
Scope - Partially replacing roof which includes the annex area, covered walkway and three classrooms.
|
Project Managers - Brian Radabaugh, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 25, 2009 |
| Estimated Finish Date July 24, 2009 |
Top of page
Seal Building Exterior |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date October 31, 2010 |
Top of page
Replace a Portion of Windows |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace a Portion of Siding |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace a Portion of Floor Coverings |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace a Portion of Ceiling Tiles |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
Estimated Finish Date August 31, 2010 |
Top of page
Replace a Portion of Bathroom Fixtures |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date April 30, 2010 |
Estimated Finish Date October 31, 2010 |
Top of page
Replace a Portion of Water Supply Lines |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date April 30, 2010 |
Estimated Finish Date October 31, 2010 |
Top of page
Upgrade Fire Alarm System |
Scope |
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 1, 2010 |
| Estimated Finish Date August 31, 2010 |
Top of page
Resurface Playground |
Scope - Resurfacing of playground and repainting of activity areas
|
Project Managers - Mathieu Jacobs, Cornerstone Management Group
- Mike Witte, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 29, 2009 |
| Estimated Finish Date August 10, 2009 |
Top of page
Four Corners Elementary
500 Elma Avenue SE
Salem, OR 97317-5621
Map