Page updated May 8, 2012
Complete List of School Repairs
| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Heating/Ventilation Rooftop Units/Chiller | June 20, 2011 | August 16, 2011 |
| Replace Portions of Damaged Floor Coverings | June 20, 2011 | August 16, 2011 |
| Replace Gym Floor | June 15, 2012 | August 27, 2012 |
| Replace Hot Water Lines | June 20, 2011 | August 16, 2011 |
| Replace Fire Alarm | June 2008 | September 18, 2008 |
| Resurface Damaged Parking Lot | June 20, 2011 | August 16, 2011 |
Replace Heating/Ventilation Rooftop Units/Chiller |
Scope - Replace Chiller / Roof Top units
- Replace Pneumatic HVAC controls with DDC controls
|
Project Managers - Adam Cormack, Cornerstone Management Group
|
Architect |
Contractor - First Cascade Corporation (General Contractor)
- Robert Lloyd Sheet Metal, Inc.
|
| Estimated Start Date June 20, 2011 |
Estimated Finish Date August 16, 2011 |
Top of page
Replace Portions of Damaged Floor Coverings |
Scope - Replace 90% of floor coverings
|
Project Managers - Adam Cormack, Cornerstone Management Group
|
Architect |
Contractor - First Cascade Corporation (General Contractor)
- Carpet Company
|
| Estimated Start Date June 20, 2011 |
Estimated Finish Date August 16, 2011 |
Top of page
Replace Gym Floor |
Scope |
Project Managers - Stephanie Farthing, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor |
| Estimated Start Date June 15, 2012 |
| Estimated Finish Date August 27, 2012 |
Top of page
Replace Hot Water Lines |
Scope - Replace domestic hot water lines in building and main line to point of connection at street.
|
Project Managers - Adam Cormack, Cornerstone Management Group
|
Architect |
Contractor - First Cascade Corporation (General Contractor)
- Oregon Cascade
|
| Estimated Start Date June 20, 2011 |
Estimated Finish Date August 16, 2011 |
Top of page
Replace Fire Alarm |
Scope - Repair and renovate wiring, devices, and fire alarm control panel
|
Project Managers - Art Merriman, Construction Services, Salem-Keizer Public Schools
|
Architect |
Contractor - Northwest Low Voltage, Inc.
|
| Estimated Start Date June 2008 |
| Estimated Finish Date September 18, 2008 |
Top of page
Resurface Damaged Parking Lot |
Scope - Resurface and restripe asphalt in portion of parking areas
|
Project Managers - Adam Cormack, Cornerston Management Group
|
Architect |
Contractor - First Cascade Corporatoni (General Contractor)
- KF Jacobsen
|
| Estimated Start Date June 20, 2011 |
Estimated Finish Date August 16, 2011 |
Top of page
Eyre Elementary
4868 Buffalo Drive SE
Salem, OR 97317-5984