Candalaria Elementary School
Last updated September 16, 2009
Complete List of School Repairs
| Projects | Estimated Start Date | Estimated Completion Date |
| Replace Exterior Seal | June 1, 2011 | August 31, 2011 |
| Replace Windows | June 1, 2011 | August 31, 2011 |
| Replace Portions of Siding | June 1, 2011 | August 31, 2011 |
| Replace Half the Steam Lines | June 1, 2011 | September 30, 2011 |
| Replace Bathroom Fixtures | June 1, 2011 | September 30, 2011 |
| Replace Water Supply Lines | June 1, 2011 | September 30, 2011 |
Replace Exterior Seal |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Windows |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Portions of Siding |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date August 31, 2011 |
Replace Half the Steam Lines |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date September 30, 2011 |
Replace Bathroom Fixtures |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date September 30, 2011 |
Replace Water Supply Lines |
Scope |
Project Managers |
Architect |
Contractor |
| Estimated Start Date June 1, 2011 |
| Estimated Finish Date September 30, 2011 |
Candalaria Elementary
935 Hansen Avenue S.
Salem, OR 97302