Auburn Elementary School

Page updated July 7, 2010

Complete List of School Repairs

Projects
Estimated Start Date
 Estimated Completion Date
Replace RoofJune 21, 2010August 31, 2010
Replace Flooring June 1, 2011August 31, 2011 
Replace Exterior SealJune 1, 2011August 31, 2011
Replace WindowsJuly 1, 2009November 30, 2009
Replace Heating/Cooling UniventsJune 1, 2011August 31, 2011
Replace Bathroom FixturesJune 1, 2011August 31, 2011
Upgrade Fire Alarms June 1, 2011 August 31, 2011
Upgrade Intercom June 1, 2011 August 31, 2011
Repair Playground Asphalt June 1, 2011 August 31, 2011

 

 

Replace Roof
 

Scope

Project Managers

  •  Brian Radabaugh, Cornerstone Management Group 

Architect

  •  Paul L. Bentley Architects

Contractor

  •  Anderson Roofing
Estimated Start Date June 21, 2010
Estimated Finish Date August 31, 2010
 

Top of page

 

 

Replace Flooring
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2010
Estimated Finish Date August 31, 2011
 

Top of page

 

  

Replace Exterior Seal
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

 

Replace Windows
 

Scope 

  • Replacing old single pane windows with energy efficient units

Project Managers

  • Mathieu Jacobs, Cornerstone Management Group
  • Mike Witte,  Construction Services, Salem-Keizer Public Schools

Architect

  • Anderson Shirley

Contractor

  • Arciform
Estimated Start Date July 1, 2009
Estimated Finish Date November 30, 2009

Top of page

 

  

Replace Heating/Cooling Univents
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

 

Replace Bathroom Fixtures
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

 

Upgrade Fire Alarms
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

 

Upgrade Intercom
 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

 

Repair Playground Asphalt 

Scope

Project Managers

  •  
  •  

Architect

  •  

Contractor

  •  
Estimated Start Date June 1, 2011
Estimated Finish Date August 31, 2011
 

Top of page

 

Auburn Elementary
4612 Auburn Rd. NE
Salem, OR 97301-491
Map

 

construction bond logo

  • Bond Updates
    • About
    • Citizen Bond Oversight Committee
    • FAQ
    • Resources
    • Schools
      • Auburn
      • Bethel
      • Brush College
      • Candalaria
      • Chapman Hill
      • Clear Lake
      • Crossler
      • Cummings
      • Englewood
      • Eyre
      • Four Corners
      • Fruitland
      • Grant
      • Gubser
      • Hayesville
      • Hazel Green
      • Highland
      • Hoover
      • Houck
      • Judson
      • Keizer
      • Kennedy
      • Lake Labish
      • Liberty
      • McKay
      • McKinley
      • McNary
      • Middle Grove
      • Morningside
      • Myers
      • North
      • Parrish
      • Pringle
      • Richmond
      • Rosedale
      • Salem Heights
      • Schirle
      • Scott
      • South
      • Sprague
      • Sumpter
      • Swegle
      • Waldo
      • Walker
      • Washington
      • West
      • Whiteaker
      • Wright
      • Yoshikai
    • Contact Us
Salem-Keizer Public Schools | 2450 Lancaster Dr. NE, Salem, Oregon 97305 | 503-399-3000.
Contact us with your comments and questions